PLN Moves 100 GWp National Solar Programme into Tendering: First Wave of 14 Projects Totals 5,216 MWp
Site surveys are complete and procurement opens soon; floating projects at Jatiluhur (1,688 MWp) and Cirata (1,250 MWp) lead the ready-to-tender list, with six early projects already under construction.
State utility PLN announced on 25 November that site surveys for the national 100 GWp solar programme are complete and the procurement process will start imminently, as stated by president director Suroso at the National Energy Forum 2026. The first wave lists 14 projects totalling 5,216 MWp. Ready for tender: floating solar at Jatiluhur (1,688 MWp), Cirata (1,250 MWp) and Jatigede (636 MWp), the Madura cluster solar-plus-BESS (605 MWp), Bali/Gilimanuk (300 MWp) and Purwakarta (69 MWp). Already in construction: Banyuwangi (130.2 MWp), Pasuruan (132 MWp), Gajah Mungkur (134.2 MWp), Karangkates (133 MWp, 56.54% progress), Saguling (92 MWp, 44.4%) and Tembesi Batam (46 MWp, 65%).
Separately, subsidiary PLN Nusantara Power opened tenders for three small hydro-thermal plants totalling roughly 120–148 MW — Tahuna II, Sumbawa-4, and Flores & Rangko-2 — with registration open until 24 February 2027 and bid submission closing 12 March 2027. Together the announcements mark the largest energy construction pipeline set in motion this year, with dam-based floating projects driving demand for site monitoring and large-scale EPC documentation through 2027–2029.