Transport 2026-11-15

KAI Commuter trials 12-car trains on Green Line, maps electrification and signaling roadmap

Six weekend trial runs run 14-15 November on the Rangkasbitung line, with four new traction substations targeted for mid-2027 and signaling renewal through 2028.

KAI Commuter began limited trials of 12-car electric trains (SF12) on the Tanah Abang-Parung Panjang section of the Rangkasbitung line, running six round trips per day on the weekend of 14-15 November between afternoon and evening hours. The operator says station platforms are ready; the remaining constraint is traction power, and it plans roughly four new substations targeted for completion by mid-2027, followed by a signaling renewal program starting late 2027 and targeted for completion by end-2028 to shorten train headways.

Demand context makes the capacity push concrete: weekend ridership on the Rangkasbitung line averaged 190,263 passengers per day in October 2026, up 3.85 percent from September. For a commuter network of this size, a dated signaling-renewal program is a multi-year systems project that will open downstream procurement packages in installation, integration, safety documentation, and operational data. In the nearer term, the trial evaluation cycle itself generates recurring operational and compliance documentation as the operator decides whether to commit to full 12-car services.