Full BIM deployment on Serang–Panimbang toll section flagged as public works pilot
The 6.29 km section, built by a PP–Adhi Karya–Waskita–Modern Widya joint operation at 93.8 percent progress, uses 4D modeling, lidar and drone scanning, VR visualization and a BIM KPI dashboard.
Public works sector media reported on 18 November 2026 that Package 3 of Section III Phase 2 of the Serang–Panimbang toll road (Cileles–Panimbang, 6.29 km) has applied building information modeling throughout its execution. The section is being built by a joint operation of PT PP (32.5 percent), Adhi Karya (30 percent), Waskita Karya (27.5 percent) and Modern Widya Technical (10 percent), with progress at 93.8 percent as of mid-September 2026.
The BIM deployment covers structural modeling of the 6.14 km slab-on-pile section and bridges, 4D model-schedule integration, quantity take-off, document coordination, construction safety, lidar and drone scanning with aerial photography, VR visualization, and a BIM dashboard tracking maturity and KPIs. Run under the Public Works Ministry's highways directorate general, the project is positioned as a candidate pilot and reference for future infrastructure projects, extending digital standardization from building programs into toll road construction.